Reference 01 / Commissioning
Dairy plant equipment commissioning guide
乳品新工厂设备调试指南
A new dairy line is commissioned phase by phase, each one gated by the last. Nothing downstream is energised until the utility feeding it is proven; no product flows until the sterile boundary holds. This guide walks the standard sequence for a Tetra Pak UHT line and the qualification evidence each phase must produce.
- Scope
- Greenfield UHT line
- Framework
- FAT → SAT → IQ → OQ → PQ
- Outcome
- Validated, handed-over line
Qualification framework
资质验证框架
Commissioning rides on a documented qualification chain. Each stage produces signed evidence; you do not advance on the strength of "it looked fine."
| Stage | 中文 | Proves | Typical evidence |
|---|---|---|---|
| FAT | 工厂验收测试 | Equipment meets spec at the vendor's works | FAT protocol, punch list |
| SAT | 现场验收测试 | Equipment performs as built on site | SAT protocol, loop checks |
| IQ | 安装确认 | Installed per drawings and P&IDs | As-built check, calibration certs |
| OQ | 运行确认 | Operates across the full design range | Sequence tests, alarm tests |
| PQ | 性能确认 | Produces to spec, repeatably, over time | 3 consecutive production runs |
Utilities readiness
公用工程就绪
Process equipment is only as reliable as the utilities behind it. Confirm each utility to its point-of-use specification before energising any machine - clean steam pressure at the holding tube, not just at the boiler header.
| Utility | Point-of-use spec | Check |
|---|---|---|
| Culinary / clean steam | ≥ 3.5 bar(g), dry, 3.9.2 quality | Pressure log + non-condensable gas test |
| Compressed air (instrument) | 6 to 8 bar(g), ISO 8573-1 Class 2.4.2 | Dew point + oil content |
| Sterile air | 0.2 µm filtered, ≥ 0.5 bar above product | Filter integrity (bubble point) |
| Process water / WFI-grade | Conductivity in spec, microbial limit | Conductivity + TOC + micro |
| Chilled water / glycol | Design ΔT at full load | Flow + supply/return temp |
| Electrical / UPS | Stable supply, UPS holdover verified | Phase rotation, UPS drop test |
Utilities checklist公用工程检查表
CIP validation - Alcip
CIP 清洗验证(Alcip)
Cleaning is validated before production, never after. The Tetra Pak Alcip station runs the standard caustic / acid / rinse program; commissioning proves every product-contact surface sees the target temperature, concentration, flow velocity, and time - the TACT parameters.
| Parameter | Target | Verified by |
|---|---|---|
| Temperature | Caustic 75 to 85 °C, acid 60 to 70 °C | RTD logging at return |
| Action (flow velocity) | ≥ 1.5 m/s turbulent in all pipework | Flow meter + pipe sizing |
| Concentration | NaOH 1.5 to 2.0%, HNO₃ 0.5 to 1.0% | Conductivity transmitter |
| Time | Per recipe, return-temp gated | PLC cycle log |
CIP program flow清洗流程
- 01
Pre-rinse预冲洗
Push product out with recovered water to drain; rinse until clear, monitored by return turbidity/conductivity. - 02
Caustic wash碱洗
Recirculate NaOH at temperature; concentration held by dosing on conductivity feedback. Removes protein and fat soils. - 03
Intermediate rinse中间冲洗
Flush caustic to drain or recovery until conductivity returns to water baseline. - 04
Acid wash酸洗
Recirculate HNO₃ to dissolve mineral scale (milkstone). Critical after thermal duty on Tetra Therm surfaces. - 05
Final rinse最终冲洗
Rinse with clean/treated water until conductivity meets the release limit. This is the release gate for the circuit.
Thermal validation - UHT / Tetra Therm
热处理验证(Tetra Therm 杀菌机)
Thermal validation proves the line delivers the required lethality without scorching product. The controlling variable is the holding tube: product must reach sterilization temperature and be held for the full residence time at the lowest expected flow, with auto-divert protecting against any excursion.
| Stage | Setpoint | Note |
|---|---|---|
| Pre-heat / regeneration | 70 to 90 °C | Energy recovery section |
| Sterilization (holding) | 137 to 142 °C, 4 to 6 s | Defines commercial sterility |
| Aseptic cooling | down to 20 to 25 °C | Before aseptic tank / filler |
| Sterilization water cycle | Hold ≥ 30 min at ≥ 130 °C | Pre-production sterilization of the circuit |
Auto-divert valve logic自动转向阀逻辑
If holding-tube outlet temperature drops below setpoint, the divert valve must redirect product to drain and the downstream aseptic boundary must respond - product behind the fault is never allowed forward. Commissioning verifies both the trigger and the timing.
Aseptic systems & tanks - Tetra Alsafe
无菌系统与缓存罐(Tetra Alsafe)
The aseptic tank decouples the steriliser from the filler so neither stops for the other. Its integrity rests on a maintained sterile air barrier and a positive overpressure that keeps the outside world out. Commissioning proves the barrier holds under every operating transition - fill, empty, and idle.
- 01
Pre-sterilization (SIP)在线灭菌
Steam the tank and connected valve clusters to temperature, holding all CCPs (steam barrier temperatures, condensate drainage) for the validated time. - 02
Sterile air pressurization无菌空气加压
Establish sterile-filtered air overpressure once cooled; the tank must never go to atmospheric while aseptic. - 03
Barrier hold test屏障保压测试
Verify the tank holds overpressure with no make-up demand beyond the expected leak rate - a pressure-decay test proves integrity. - 04
Level cycling液位循环
Run fill/draw cycles; confirm vacuum-relief and overpressure controls keep headspace pressure inside band during fast level changes.
| Control | Function | Failure response |
|---|---|---|
| Sterile air barrier | Positive pressure vs. ambient | Loss of sterility alarm → quarantine |
| Valve cluster (steam barrier) | Steam-blocked double-seat at boundaries | Barrier temp low → close to product |
| Pressure monitoring | Headspace within validated band | High/low alarm + control action |
| Vacuum relief | Prevents collapse on fast draw-down | Sterile-air make-up on demand |
Aseptic filling IQ/OQ/PQ - A3 / Flex
无菌灌装确认(A3/Flex 灌装机)
The filler is where sterility meets the package. Qualification walks the IQ/OQ/PQ chain: confirm it is installed correctly, prove it operates across its range, then prove it makes good packages, run after run.
| Stage | Activity | Acceptance |
|---|---|---|
| IQ | Verify install vs. drawings; calibrate sensors; confirm H₂O₂ system, web path, services | Signed install check, calibration certs |
| OQ | Sterilization cycle, sealing parameter windows, alarm and divert tests, fill-volume accuracy | All sequences pass across range |
| PQ | 3 consecutive production runs at rate | Sterility + seal integrity + fill weight in spec |
Sealing & package integrity封口完整性
Both seals are proven: the longitudinal seal (strip-applied and welded as the web forms a tube) and the transverse seal (the jaw system closing each package). Destructive tear-down, tightness, and dye-penetration tests confirm there is no channel for recontamination.
Troubleshooting checklists
故障排查清单
The faults that actually stall a commissioning, with the first checks that resolve most of them.